Projektek-Tapolca
601 kWp
ÉCS
The project will be built on a 1,2 ha area in the outskirts of the city of Écs, Hungary. The number of mounted power plants is 1 x 468 kVA. The expected completion of the project: 2022 Q3.
PROJECT DETAILS:
-
Project Owner: Écs Helyi Önkormányzat
-
Number of power plants: 1 x 468 kVA
-
Location: Écs, Hungary
-
Land Area: 1,2 ha
-
Nominal DC power: 1 x 601,12 kWp
-
Expected date of the end of construction: 2022 Q3
-
Energy Sale: 1 x 25 year KÁT license